The project will see seven fire stations rebuilt as well as the construction of an additional three stations where additional resources are required.
The new additional stations to be built are Tamworth, at a location in Belgrave (the existing Tamworth station will also be rebuilt on its current site at Lichfield Street), Sandyford which is located between Kidsgrove and Burslem in North Staffordshire and Rising Brook which will complement the existing station at Beaconside, Stafford. The table below details when construction is due to commence and be completed.
All stations have been designed with a community facility and state of the art operational facilities.
| Station | Status | Start Date | Completion |
| Rising Brook, Stafford | Retained | Aug 2009 | July 2010 |
| Sandyford | Wholetime | Oct 2009 | Oct 2010 |
| Belgrave, Tamworth | Wholetime | Nov 2009 | Nov 2010 |
| Uttoxeter | Retained | Nov 2009 | Feb 2011 |
| Cannock | Wholetime | Jan 2010 | Jan 2011 |
| Hanley | Wholetime | Mar 2010 | July 2011 |
| Newcastle | Wholetime | Sep 2010 | Aug 2011 |
| Burslem | Retained | Sep 2010 | Aug 2011 |
| Kidsgrove | Retained | Sep 2010 | Aug 2011 |
| Lichfield Street, Tamworth | Retained | Oct 2010 | Sep 2011 |